Close
Mining News

The Update on the Abcourt-Barvue Feasibility Study is Positive. A Major Reduction in the Initial Capital Cost is Expected

Rouyn-Noranda, Quebec, Canada / TheNewswire / February 8, 2019 - Abcourt Mines Inc. (TSX-V: ABI, Berlin: AML-BE and Frankfurt Stock Exchanges: AML-FF) ("Abcourt" or the "Company is announcing positive results for the feasibility study update on the Abcourt-Barvue project and a major reduction in the initial capital cost.

The Abcourt-Barvue property was in production by an open pit and an underground mine during two different periods. The project consists of three open pits, namely Barvue, Abcourt East and Abcourt West, and the development of an underground mine to produce a zinc-silver concentrate

This National Instrument 43-101 Technical Report on the Abcourt-Barvue Project was prepared to present the findings of an update to the Technical Feasibility Study Report on the Abcourt-Barvue Deposit dated February 15, 2007, prepared by Genivar and Bumigene and filed on Sedar.

The Abcourt-Barvue Project is located in the Abitibi area, northwestern Quebec, Canada, 60 km north of the town of Val d'OrThe project is located on an existingmine site with several readily useablinfrastructuresin a very easilaccessiblarea where all services may be obtained at competitive prices.

Abcourt commissioned PRMining Services Inc(PRB) and Bumigeme Inc. (Bumigemeto update the 2007 feasibility study using current economic parameters, theGenivar 2007 pit design, anmodifying the process flowsheet to eliminatthe silver cyanidation circuit and to produce only zinc-silver concentrate by flotation.

HISTORY

The zinc-silver mineralization was discovered in 1950. The Abcourt-Barvue deposit was in operation during two periods: between 1952 and 1957 by Barvue MinesLimited and between 1985 and 1990 by Abcourt. In all 5,002,19metric tonnes grading 38.74 g/t Ag and 2.98% Zn were mined from the Barvue open pit and632,319 metric tonnes grading 131.65 g/t Ag an5.04% Zn were mined from underground productionThe old Barvue tailings ponwas recently rehabilitated by the Ministry of Natural Resources of the province oQuebec. Abcourretained the mining concessions and surrounding cells to this day.

MINERAL RESOURCES

A mineral resource estimate was produced by Jean-Pierre Berube in 2014 titled NI 43-10Mineral Resources Report for the Abcourt-Barvue Property. The estimate returned measured and indicated resources (M&I) for the Abcourt-Barvue deposit totalling 8,086,000 tonnes grading 3.06% Zn and 55.38 g/t. These resources were used as a basis for the current update of the 2007 feasibility study.

Here is a comparative table of resources in all categories:

Resources of all categories

2006 Estimate 2014 Estimate

CATEGORY

TONNES

Ag (g/t)

Zn (%)

TONNES

Ag (g/t)

Zn (%)

Measured

6,516,000

58.32

3.33

6,284,000

43.98

3.09

Indicated

503,000

98.35

3.44

1,799,000

95.51

2.94

M + I

7,019,000

61.19

3.33

8,083,000

55.45

3.06

Inferred

1,506,000

120.53

2.98

2,037,000

114.16

2.89

The measured resources are generally extending from surface to a maximum depth of 165 meters. The indicated resources are generally located in the immediate extensions of the measured blocks from elevation -125 to -300 m.

The Berube report was filed on Sedar and is available for additional information.

MINERAL RESERVE ESTIMATE

The 2018 mineral reserve estimate including dilution is presented in the following table in comparison with the 2007 estimate.

Mineral Reserves

2007 Estimate

2018 Estimate

Tonnage

Grade

Tonnage

Grade

Method of Mining

Classification

Ag

Zn

Zn EQ

Ag

Zn

Zn EQ

(t)

(g/t)

(%)

(%)

(t)

(g/t)

(%)

(%)

Open Pit

Proven Mineral Reserves

5,338,731

44.79

3.15

4.03

6,180,510

39.72

2.83

3.61

Probable Mineral Reserves

0

0.00

0.00

0.00

408,851

43.01

2.36

3.20

Total Open Pit

5,338,731

44.79

3.15

4.03

6,589,361

39.93

2.80

3.58

Underground

Proven Mineral Reserves

1,169,662

105.19

2.87

4.93

1,169,662

105.19

2.87

4.93

Probable Mineral Reserves

315,139

101.61

3.23

5.22

315,139

101.61

3.23

5.22

Total Underground

1,484,801

104.43

2.95

5.00

1,484,801

104.43

2.95

4.99

Open Pit and underground

Proven Mineral Reserves

6,508,393

55.64

3.10

4.19

7,350,172

50.14

2.84

3.82

Probable Mineral Reserves

315,139

101.61

3.23

5.22

723,990

68.52

2.74

4.08

Total

6,823,532

57.76

3.11

4.24

8,074,162

51.79

2.83

3.84

Note: 1) Zn Eq grades are calculated with 2018 parameters for this table.

2) Silver zinc equivalence: 0,61% / Oz Ag

MINING PLAN

A mine plan was developed for the 2018 mineral reserves using the Genivar (now WSP Canada) 2007 pit design and underground mine design. The 2014 mineralresource diluted and recovered produced a total of 8,074,162 tonnes of mill feed grading 2.83% Zn and 51.79 gpt Ag, of which 6,589,361 tonnes (81.6%) will be produced in open pit operations and 1,484,801 tonnes (18.4%) will be produced in underground operations. The life of mine is 13 years. There argood possibilitiesof increasing the lifof mine by converting inferred resources into proven and probable reserves and by finding nereserves with additional exploration.

The open pit operation consists in the expansion and deepening of the Barvue pit and the excavatioof the Abcourt East and the AbcourWest pits over a period of13 years. The pits will be excavated to a depth of 166 m, 7m, and 4m respectively. The underground operations consist in the mining of stopes from a depthvarying from 150 m to 200 m below surface tthe pit bottoms using the Avoca method. The underground work areas will be accessed by excavating declines.

MINERAL PROCESSING

Historical mineral recoveries during the Barvue production period were over 90% for zinc and 77% for silver. In 2017, metallurgical tests were performed in severallaboratories. The cycliflotatiotestrealized on the oroAbcourt-Barvue have showthe possibilittrecover 97.5% of the zinc and 77.8% of the silver in a Zn-Ag concentrate assaying 53.4% Zn and 740.g/tm Ag.

The processing plant remains at a mill capacity of 650,000 tonnes per year but the circuit was modified by eliminating the cyanidation circuits to produce only a zinc-silver concentrateMinor changes were brought to the surface infrastructure such as the installation of new 25kV power line on the site and threlocation of thewaste rock stockpiles.

An average of 32,000 tonnes of zinc-silver concentrate grading 52.7% Zn and 768 gpt Ag will be produced annually.

ECONOMIC ANALYSIS

The project preproduction capital cost is estimated to CA $41.including a working capital of CA $ 4.0 M, and the sustaining capital cost is estimated tCA $18.M. The average operating cost is estimated to CA $ 39.94 tonne milled. Closure costs are estimated at CA $ 3.7 M.

A reduction in the initial capital cost including working capital, from CA $ 71.26 M in 2007 to CA $ 41.3 M in 2018 was possible after the purchase during the past few years of mill equipment, now on the site, and the rental of pit equipment in 2018 instead of the purchase in 2007.

Here is a table comparing the results of the 2018 with the 2007 economic analysis for the Abcourt-Barvue silver-zinc project:

For 100% equity financing

2007

$

2018

$

Operating profit

234.3 M

225.4 M

Pre-tax cash flow

138.7 M

170.0 M

After tax cash flow

87,9 M

106,7 M

Pre-tax internal rate of return (IRR)

27.1%

26.1%

After tax internal rate of return (IRR)

21.4%

20.5%

Pre-tax net present value (NPV) 5%

87.6M

100.4 M

After tax net present value (NPV) 5%

53.2 M

59.8 M

In 2018, project revenues were estimated using US $ 1.10 per pound of zinc, US $ 16.50 per of ounce silver, an exchange rate of CA $ 1.25 per US $, and smelting & refining terms. The average net value of the ore is CA $ 67.86 per tonne.

In 2007, project revenues were estimated using US $ 1.15 per pound zinc, US $ 9.54 per ounce silver, an exchange rate of CA $ 1.15 per US $ 1.00. The average net value of the ore was CA $ 67.51 per tonne.

The 2018 economic analysis, with metal prices and the rate of exchange indicated previously assuming 100% equitfinancing, results in a pre-tax cash flow of 170.0million Canadian dollars and $106.7 M $ after taxes. The pre-tax rate of retur(IRR) is 26.1% and 20.5% after taxes. The pre-tax net present value (NPV) is 100.4 million Canadian dollars, 59.9 M $ after taxes, using a 5% discount rate. The pre-tax payback period is 4.9 years. A sensitivity analysis on revenue, capital cost, andoperating cost shows the project is most sensitivto total revenue, (price of zinc and rate of exchange) followed by operating costs.

In comparison, the Genivar 2007 study's economic analysis, with metal prices and the rate of exchange indicated on the previous page, assuming 100% equityfinancing, returned a pre-tax cash flow of 138.7 million Canadian dollars, 87.9 M $ after taxes. The pre-tax IRR is 27.1%, 21,4% after taxes, and pre-tax NPV at 5%discount rate of 87.6 million Canadian dollars, 53.2 M $ after taxes.

This report will be filed on Sedar within 45 days of this press release.

STRATEGY AND OUTLOOK

Currently, the Company is focussing on stabilizing and increasing the Elder production. Our objective is to produce 12,500 tonnes per month of gold mineralization.

We wish to use the full capacity of the Sleeping Giant mill by treating custom ore, to reduce the operating cost per tonne treated.

For the long-term growth in the gold sector, the Company has started a drilling program on the Discovery and Flordin gold properties where substantial gold mineralization is found.

For the long-term in the zinc sector, various plans are being considered.

ABOUT ABCOURT MINES INC.

Abcourt Mines Inc. is a gold producer and a Canadian exploration company with strategically located properties in northwestern Quebec, Canada. The Elder property has gold resources (2018) and a positive P.E.A. study (2012). Abcourt is focusing on the exploitation of the Elder mine.

The Abcourt-Barvue property has silver-zinc reserves (2019). A feasibility study was completed in 2007 by Roche / Genivar. An update was completed in January 2019.

In 2016, Abcourt acquired the Sleeping Giant mine and mill, located half-way between Amos and Matagami, in Abitibi, Quebec, in the territory covered by the Plan Nord of the Quebec government. The mill has a capacity of 700 to 750 tonnes per day. A NI 43-101 resource estimate was recently filed. Some custom milling is now being done.

To know more about Abcourt Mines Inc. (TSXV: ABI), please visit our web site at www.abcourt.com and consult our filings under Abcourt's profile on www.sedar.com.

This press release was prepared by Mr. Renaud Hinse, Engineer and President of Abcourt Mines Inc. Mr. Hinse is a "Qualified Persons" under the terms of Regulation 43-101. Mr. Hinse has approved the scientific and technical disclosure.

FORWARD LOOKING STATEMENTS

This news release contains forward-looking statements that include risks and uncertainties. When used in this news release, the words "estimate", "project", "anticipate", "expect", "intend", "believe", "hope", "may" and similar expressions, as well as "will", "shall" and other indications of future tense, are intended to identify forward-looking statements. The forward-looking statements are based on current expectations and apply only as of the date on which they are made. Except as may be required by law, the Corporation undertakes no obligation and disclaims any responsibility to publicly update or revise any forward-looking statements or information, whether as a result of new information, future events or otherwise.

The factors that could cause actual results to differ materially from those indicated in such forward-looking statements include changes in the prevailing price of gold, the Canadian-United States exchange rate, grade of ore mined and unforeseen difficulties in mining operations that could affect revenue and production costs. Other factors such as uncertainties regarding government regulations could also affect the results. Other risks may be set out in Abcourt' annual and periodic reports. The forward-looking information contained herein is made as of the date of this news release.

For more information, please contact:

Renaud Hinse, President and CEO

: 819 768-2857 450 446-5511

: 819 768-5475 450 446-3550

Email: rhinse@abcourt.com

Dany Cenac Robert, Investor Relations

Reseau ProMarket Inc.,

T: (514) 722-2276 x456

Dany.Cenac-Robert@ReseauProMarket.com

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.